Encouraging results from Ngala Hill
sampling program
HIGHLIGHTS
Assays include:
•
o
2.5g/t 2PGE+Au on a pyroxenite sample NGE002
o
over 23% of the samples returned 0.2 g/t 2PGE+Au. Mineralisation is hosted in
variants of pyroxenites in the licence area
o
elevated zinc grade at 3.5% Zn with associated 0.7% Cu on a meta-pyroxenite
sample NGE011
•
A total of 52 samples including soil and rock chip samples were taken to follow up on
known high grade areas as well as aiming to expand the zone of mineralisation (Figure
1).
•
At Ngala Hill, 3 key target zones of palladium rich zone with Pd+Pt+Au+Cu
mineralisation have been identified from historical trenching and limited drill testing
•
No significant modern exploration including electromagnetics (EM) to target massive
sulphides has been undertaken at Ngala Hill
•
Trenching by Placer Dome in 2000 included results of:
o
12m at 3g/t PGE+Au; and
o
70m at 1.12g/t PGE+Au, including 8m at 3.3g/t PGE+Au
The main mineralised zone has only undergone limited modern drilling
•
DY6 Metals Ltd (ASX: DY6) (“DY6”, the “Company”), a strategic metals explorer targeting Heavy Rare
Earths (HREE) and Niobium (Nb) in southern Malawi, is pleased to report the results from its recent
reconnaissance sampling program at the Ngala Hill PGE, Cu, Ni project in southern Malawi.
The assay results returned from the sampling exercise have demonstrated the potential of this Project to
host PGE and base metals mineralisation:
•
the 2.5g/t 2PGE+Au grade in the pyroxenite sample resulting from the microscopic interstitial
sulphides observed in the sample (Figure 2). The interstitial sulphide mineralisation in the
licence area will be used as a pathfinder to uncover the orebody;
•
a quarter of the sample population returning 0.2g/t 2PGE+Au which presents an upside of the
licence area (Figure 1); and
•
elevated zinc grades of 3.5% Zn with associated 0.7% Cu in a meta-pyroxenite (sample
NGE011) confirms the occurrence of base metals in the licence area which requires further
investigation.
Registered Office
Level 8, 99 St Georges Terrace
Perth WA 6000
P: +61 8 9486 4036
E: info@dy6metals.com
dy6metals.com
Figure 1: Ngala PGE Project – sample results and location
dy6metals.com | ASX:DY6 2
Figure 2: Sulphide-stained sample NGE002 returned 2.5g/t 2PGE+Au
dy6metals.com | ASX:DY6 3
Future work at Ngala Hill will focus on following up zones of higher-grade PGEs, nickel and copper with
additional sampling.
Figure 3: Location of the Ngala Hill PGE Project in southern Malawi
Background on the Project
The Ngala Hill ultramafic chonolith is an arcuate-shaped intrusion, with dimensions of approximately
2.4km by 0.7km and was intruded into the underlying Proterozoic Basement Complex gneisses. The
Ngala Hill Project is characterised by an intrusive ultramafic suite of pyroxenites and hornblendepyroxenites that intrude basement gneisses. The pyroxenite facies of the ultramafic complex is
prospective for platinum group elements (PGEs), predominantly palladium, and associated copper.
Initial work at Ngala Hill in the late 1960s included geochemical sampling programs undertaken by the
British and Malawian Geological Surveys. Phelps Dodge started an exploration program for PGEs on
Ngala Hill in 1999 with approximately 600 m of trenching. Metapyroxenite and amphibolite with an PGEgold-copper nickel association was intersected trenching and yielded 1.41g/t Pt+Pd+Au and 1,430 ppm
Cu over a length of 64m.
In 2000, Placer Dome confirmed further anomalies with encouraging results received from several
trenches including 12m at 3g/t PGE+Au and 70 m at 1.12g/t PGE+Au, including 8m at 3.3g/t PGE+Au.
dy6metals.com | ASX:DY6 4
Three zones of palladium-platinum-gold-copper mineralisation were defined at Ngala Hill, including:
•
Main Zone striking parallel to the main spine of Ngala Hill for approximately 2 km;
•
Massive Sulphide Zone comprising laminated, outcropping 10 cm thick massive sulphide band
with associated quartz breccias; and
•
Western Sill potentially mineralised at a similar topographic level to the Main Zone.
Figure 4: Ngala Hill PGE Project area crops out as a kidney shaped ultramafic Intrusion
dy6metals.com | ASX:DY6 5
-ENDSThis announcement has been authorised by the Board of DY6.
More information
Mr Dan Smith
Mr John Kay
Mr Luke Forrestal
Non-Executive Chairman
Director & Company Secretary
Investor Relations
dan.smith@dy6metals.com
john.kay@dy6metals.com
+61 411 479 144
Competent Persons Statement
The Information in this announcement that relates to exploration results, mineral resources or ore reserves
is based on information compiled by Mr Allan Younger, who is a Member of the Australasian Institute of
Mining and Metallurgy. Mr Younger is a consultant of the Company. Mr Younger has sufficient experience
which is relevant to the style of mineralisation and type of deposits under consideration and to the activity
that he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the `Australian
Code for Reporting Exploration Results, Mineral Resources and Ore Reserves’ (the JORC Code). Mr
Younger consents to the inclusion of this information in the form and context in which it appears in this
announcement. Mr Younger holds shares in the Company.
dy6metals.com | ASX:DY6 6
Table 1. Ngala Project Geochemical Sampling Assay Results
FIELD
SAMPLE
ID
Easting
Northing
Elevation
Datum
Weight
(g)
NGE001
704600
8222484
239
WGS Z36S
312.66
NGE002
704699
8222493
279
WGS Z36S
295.89
NGE003
704700
8222390
296
WGS Z36S
NGE004
704601
8222393
263
NGE005
704494
8222304
NGE006
704605
NGE007
Au
(ppm)
Pt
(ppm)
Pd
(ppm)
Rh
(ppm)
0.04
0.03
0.11
0.01
0.02
0.68
1.83
0.01
316.28
0.005
0.03
0.05
WGS Z36S
301.33
0.005
0.02
248
WGS Z36S
314.43
0.005
8222296
268
WGS Z36S
302.21
704699
8222295
285
WGS Z36S
NGE008
706005
8221488
216
NGE009
705988
8221884
333
NGE010
705994
8221975
NGE011
705981
NGE012
Co
(%)
Zn (%)
2PGE +
Au (g/t)
0.01
0.01
0.18
0.01
0.005
2.53
0.005
0.01
0.005
0.09
0.005
0.005
0.01
0.005
0.08
0.0025
0.005
0.005
0.01
0.005
0.11
0.18
0.0025
0.005
0.005
0.01
0.005
0.13
7.52
0.15
0.0025
0.03
0.005
0.01
0.005
0.09
0.01
7.98
0.16
0.0025
0.005
0.005
0.01
0.005
0.06
0.005
7.29
0.15
0.0025
0.005
0.005
0.01
0.005
0.08
0.005
7.7
0.17
0.0025
0.005
0.005
0.01
0.01
0.04
0.005
0.65
29.84
2.21
0.0025
0.005
0.005
0.01
3.52
0.09
0.005
0.02
0.005
7.62
0.16
0.0025
0.01
0.005
0.01
0.005
0.26
0.01
0.005
0.005
0.005
7.94
0.15
0.0025
0.005
0.005
0.01
0.005
0.02
0.1
0.01
0.005
0.01
0.01
8.6
0.15
0.0025
0.005
0.005
0.01
0.005
0.15
0.03
0.08
0.01
0.005
0.01
0.005
7.58
0.16
0.0025
0.005
0.005
0.01
0.005
0.12
0.06
0.08
0.01
0.005
0.005
0.005
7.33
0.14
0.0025
0.005
0.005
0.01
0.005
0.19
0.005
0.03
0.06
0.01
0.005
0.03
0.01
8.01
0.16
0.0025
0.02
0.005
0.01
0.005
0.10
324.89
0.02
0.05
0.15
0.01
0.005
0.005
0.03
9.37
0.17
0.0025
0.03
0.005
0.01
0.005
0.22
WGS Z36S
322.42
0.01
0.04
0.08
0.01
0.005
0.02
0.005
7.55
0.15
0.0025
0.02
0.005
0.01
0.005
0.13
319
WGS Z36S
316.33
0.02
0.04
0.06
0.01
0.005
0.02
0.005
8.05
0.17
0.0025
0.02
0.005
0.01
0.005
0.12
8221790
354
WGS Z36S
307.98
0.005
0.04
0.1
0.01
0.005
0.03
0.005
6.28
0.14
0.0025
0.01
0.005
0.01
0.005
0.15
705702
8221708
344
WGS Z36S
307.47
0.005
0.04
0.04
0.01
0.005
0.02
0.005
9.77
0.15
0.0025
0.02
0.005
0.01
0.005
0.09
NGE023
705602
8221701
330
WGS Z36S
313.08
0.01
0.03
0.06
0.01
0.005
0.03
0.005
7.61
0.16
0.0025
0.02
0.005
0.01
0.005
0.10
NGE024
705613
8221786
346
WGS Z36S
310.59
0.01
0.04
0.06
0.01
0.005
0.03
0.005
7.36
0.14
0.0025
0.02
0.005
0.01
0.005
0.11
NGE025
705503
8221790
302
WGS Z36S
310.14
0.01
0.01
0.05
0.01
0.005
0.01
0.005
8.14
0.15
0.0025
0.005
0.005
0.01
0.005
0.07
NGE026
705503
8221691
312
WGS Z36S
284.3
0.005
0.02
0.02
0.01
0.005
0.02
0.005
7.17
0.14
0.0025
0.01
0.005
0.01
0.005
0.05
Cr (%)
Cu (%)
Fe (%)
0.005
0.02
0.02
7.19
0.005
0.01
0.03
8.07
0.01
0.005
0.02
0.01
0.05
0.01
0.005
0.02
0.03
0.07
0.01
0.005
0.01
0.04
0.08
0.01
310.51
0.005
0.04
0.04
WGS Z36S
308.66
0.005
0.01
WGS Z36S
303.86
0.005
0.02
351
WGS Z36S
309.61
0.01
8222085
302
WGS Z36S
303.44
705854
8222294
323
WGS Z36S
NGE013
705871
8222186
332
NGE014
705882
8222097
NGE015
705907
NGE016
705808
NGE017
Mn
(%)
Pb
(%)
Mo (%)
Ni (%)
0.16
0.0025
0.005
0.01
0.13
0.0025
0.005
0.005
7.95
0.15
0.0025
0.03
0.005
8.27
0.18
0.0025
0.01
0.005
7.41
0.16
0.005
0.02
0.005
8.95
0.01
0.005
0.03
0.005
0.04
0.01
0.005
0.005
0.05
0.01
0.005
0.02
0.02
0.005
0.01
0.005
0.04
0.02
0.03
0.04
0.01
0.005
311.89
0.005
0.06
0.19
0.01
WGS Z36S
314.12
0.005
0.005
0.005
336
WGS Z36S
313.82
0.02
0.03
8221898
392
WGS Z36S
281.96
0.005
8221797
368
WGS Z36S
329.56
0.05
705804
8221996
328
WGS Z36S
317.49
NGE018
705808
8222093
309
WGS Z36S
NGE019
705799
8222188
325
NGE020
705702
8221892
NGE021
705702
NGE022
W (%)
dy6metals.com | ASX:DY6
7
FIELD
SAMPLE
ID
Easting
Northing
Elevation
Datum
Weight
(g)
NGE027
705399
8221589
272
WGS Z36S
297.33
NGE028
705403
8221689
302
WGS Z36S
NGE029
705412
8221792
281
NGE030
705304
8221693
NGE031
705310
NGE032
NGE033
Au
(ppm)
Pt
(ppm)
Pd
(ppm)
Rh
(ppm)
0.01
0.03
0.13
0.01
280.95
0.005
0.02
0.06
WGS Z36S
317.37
0.02
0.04
273
WGS Z36S
303.71
0.01
8221598
261
WGS Z36S
308.32
705192
8221583
227
WGS Z36S
705200
8221693
268
WGS Z36S
NGE034
705104
8221791
290
NGE035
705091
8221588
NGE036
705002
NGE037
Co
(%)
Mo (%)
Ni (%)
Pb
(%)
W (%)
Zn (%)
2PGE +
Au (g/t)
0.15
0.0025
0.005
0.005
0.01
0.005
0.17
8.35
0.16
0.0025
0.005
0.005
0.01
0.005
0.09
0.005
8.35
0.17
0.0025
0.005
0.005
0.01
0.005
0.14
0.02
0.005
7.88
0.17
0.0025
0.005
0.005
0.01
0.005
0.07
0.005
0.02
0.01
9.94
0.15
0.0025
0.02
0.005
0.01
0.005
0.10
0.01
0.005
0.01
0.01
0.005
0.01
0.005
7.84
0.15
0.0025
0.005
0.005
0.01
0.005
0.18
0.02
8.46
0.16
0.0025
0.01
0.005
0.01
0.005
0.17
0.04
0.01
0.005
0.03
0.005
6.78
0.14
0.0025
0.01
0.005
0.01
0.005
0.08
0.02
0.03
0.01
0.005
0.06
0.01
6.6
0.14
0.0025
0.005
0.01
0.01
0.005
0.06
0.02
0.07
0.08
0.01
0.005
0.02
0.02
7.52
0.16
0.0025
0.02
0.005
0.01
0.005
0.17
313.68
0.02
0.05
0.14
0.01
0.005
0.01
0.005
7.52
0.14
0.0025
0.005
0.005
0.01
0.005
0.21
WGS Z36S
318.58
0.02
0.21
0.3
0.01
0.005
0.01
0.03
7.65
0.15
0.0025
0.02
0.005
0.01
0.005
0.53
328
WGS Z36S
323.43
329
WGS Z36S
297.76
0.01
0.04
0.08
0.01
0.005
0.02
0.005
7.09
0.14
0.0025
0.01
0.005
0.01
0.005
0.13
0.02
0.02
0.06
0.01
0.005
0.02
0.01
7.15
0.16
0.0025
0.005
0.005
0.01
0.005
0.10
8221586
251
WGS Z36S
297.97
0.03
0.02
0.05
0.01
0.005
0.02
0.03
7.32
0.14
0.0025
0.01
0.005
0.01
0.005
0.10
704903
8221990
304
WGS Z36S
296
0.005
0.05
0.08
0.01
0.005
0.03
0.005
7.5
0.14
0.0025
0.02
0.005
0.01
0.005
0.14
NGE043
704797
8221692
275
WGS Z36S
311.43
0.005
0.04
0.1
0.01
0.005
0.02
0.005
6.27
0.14
0.0025
0.01
0.005
0.01
0.005
0.15
NGE044
704799
8221789
315
WGS Z36S
303.53
0.02
0.03
0.08
0.01
0.005
0.02
0.005
7.73
0.17
0.0025
0.005
0.005
0.01
0.005
0.13
NGE045
704807
8221888
324
WGS Z36S
310.98
0.005
0.02
0.03
0.01
0.005
0.02
0.005
6.66
0.15
0.0025
0.005
0.005
0.01
0.005
0.06
NGE046
704799
8221996
322
WGS Z36S
305.41
0.01
0.04
0.1
0.01
0.005
0.03
0.01
7.27
0.16
0.0025
0.005
0.005
0.01
0.005
0.15
NGE047
704799
8222094
292
WGS Z36S
323.66
0.005
0.02
0.06
0.01
0.005
0.04
0.005
6.86
0.14
0.0025
0.005
0.005
0.01
0.005
0.09
NGE048
704706
8222195
264
WGS Z36S
288.58
0.005
0.02
0.05
0.01
0.005
0.03
0.005
7.28
0.15
0.0025
0.005
0.005
0.01
0.005
0.08
NGE049
704708
8222096
275
WGS Z36S
298
0.01
0.02
0.06
0.01
0.005
0.03
0.005
7.54
0.15
0.0025
0.005
0.005
0.01
0.005
0.09
NGE050
704710
8221979
283
WGS Z36S
297.27
0.005
0.02
0.07
0.01
0.005
0.04
0.005
6.72
0.16
0.0025
0.005
0.005
0.01
0.005
0.10
NGE051
704599
8222089
256
WGS Z36S
323.3
0.005
0.01
0.04
0.01
0.03
0.03
0.005
6.19
0.14
0.0025
0.005
0.005
0.01
0.005
0.06
NGE052
704609
8222200
253
WGS Z36S
329.14
0.005
0.005
0.005
0.01
0.005
0.02
0.005
8.14
0.14
0.0025
0.005
0.005
0.01
0.005
0.02
Cr (%)
Cu (%)
Fe (%)
0.005
0.02
0.005
7.21
0.01
0.005
0.02
0.005
0.08
0.01
0.005
0.02
0.03
0.03
0.01
0.005
0.005
0.04
0.05
0.01
309.68
0.005
0.04
0.13
309.11
0.05
0.04
0.08
WGS Z36S
308.73
0.005
0.03
253
WGS Z36S
294.87
0.005
8221596
264
WGS Z36S
330.46
705004
8221692
297
WGS Z36S
NGE038
704998
8221787
326
NGE039
704903
8221897
NGE040
704896
8221789
NGE041
704898
NGE042
Mn
(%)
dy6metals.com | ASX:DY6
8
Annexure A: JORC Code, 2012 Edition – Table 1 report
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
JORC Code explanation
Sampling
techniques
•
•
•
•
Drilling
techniques
•
Commentary
Nature and quality of sampling (e.g. cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should not
be taken as limiting the broad meaning of sampling.
Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
Aspects of the determination of mineralisation that are Material to
the Public Report.
In cases where ‘industry standard’ work has been done this would be
relatively simple (e.g. ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverized to produce a 30 g charge
for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (e.g.
submarine nodules) may warrant disclosure of detailed information.
•
Drill type (e.g. core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (e.g. core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
•
•
•
Grid sampling at approximately 100m by 100m was used and field
rock chip samples of outcrop were taken by field staff from outcrops
utilising a geo-pick, 3.5kg hammer and a chisel.
The planned sampling grid used ensured samples are taken without
bias. The grid extended through the various lithological units of the
orebody thereby ensuring a reasonable sample representivity.
Mineralisation was visually determined as in cases of malachite for
possible copper mineralisation and sulphide staining. A hand lens
was used to determine microscopic sulphide mineralisation.
No recent drilling is utilised on this program or reported in this
announcement.
dy6metals.com | ASX:DY6
9
Drill sample
recovery
•
•
•
Logging
Criteria
•
Method of recording and assessing core and chip sample recoveries
and results assessed.
Measures taken to maximise sample recovery and ensure
representative nature of the samples.
Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
•
No recent drilling done and therefore no drill sample recoveries to
report.
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
•
Qualitative geological logging of rock chips and outcrops is
completed in the field.
JORC Code explanation
Sub-sampling
techniques and
sample preparation •
•
•
•
•
Mineral Resource estimation, mining studies and metallurgical
studies.
Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
The total length and percentage of the relevant intersections logged.
If core, whether cut or sawn and whether quarter, half or all core
taken.
If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
Commentary
•
•
•
•
Logging of rock chips was done both qualitatively and quantitively.
Logged and recorded estimated minerals present in each rock chip
sample in percentages, lithology / rock types and sample weights
were taken. Location of the sample was also recorded. A
photograph of each was taken. The original was then placed in a
clearly labelled bag with a sample ticket inserted inside the bag
and another outside.
Initial Sample Preparation: Samples were crushed to -10mm using
a small portable crusher.
Quality control: the swing jaw, fixed jaw and the cheek plates for
the portable crusher were cleaned before putting in a new sample
to avoid contamination. Additionally, AMIS0450 CRM (Certified
Reference Material) and a Blank were inserted in the sample
stream at a frequency of 1 in every 20 samples to monitor
contamination and accuracy at the analysis laboratory.
Each sample was taken as a channel cut in the outcrop wherever
possible and the whole sample from one channel was crushed and
homogenised, no material was disposed of. Sufficient sample
dy6metals.com | ASX:DY6
10
•
•
•
Quality of assay
data and laboratory
tests
•
•
Measures taken to ensure that the sampling is representative of the
in situ material collected, including for instance results for field
duplicate/second-half sampling.
Whether sample sizes are appropriate to the grain size of the
material being sampled.
The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is considered
partial or total.
For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including
instrument make and model, reading times, calibrations factors
applied and their derivation, etc.
Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable
levels of accuracy (i.e. lack of bias) and precision have been
established.
•
•
•
•
•
•
•
•
material was collected for each sample ranging from 1.0 – 1.5 kg
to accommodate duplicates (if required).
Sample sizes collected were much bigger than the grain size of the
host pyroxenites being sampled. However, the size was taken care
of during sample preparation process.
A 300g portion of each of the -10mm crushed and homogenised
samples were sent to an accredited SGS Laboratory in South
Africa.
The samples were weighed on receipt at the laboratory and then
dried at 1050C
The samples were then crushed to -2mm and pulverised to 75µm.
A 30g aliquot for each sample was analysed for Au, Pt, Pd by fire
assay with an ICP-OES finish at a detection limit of 0.01 -100g/t.
This is considered a partial technique because the same sample
had to be analysed for Rh at a different ore grade detection limit of
0.02 g/t.
The samples were further analysed for base metals by
Pyrosulphate Fusion with an XRF finish.
Quality Control: in addition to the CRMs and blanks inserted in the
sample stream by the geologists, the laboratory analysed 6 AMIS
CRMs and 6 blanks to ensure accuracy.
A review of all the data in terms of QAQC revealed that the
sampling, the preparation and assaying procedures were
satisfactory.
dy6metals.com | ASX:DY6
11
Verification of
sampling and
assaying
•
•
•
•
Location of data
points
Criteria
Data spacing and
distribution
•
•
•
•
•
•
Orientation of data •
in relation to
geological
structure
•
Sample security
The verification of significant intersections by either independent or
alternative company personnel.
The use of twinned holes.
Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
Discuss any adjustment to assay data.
Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations
used in Mineral Resource estimation.
JORC Code explanation
Specification of the grid system used.
Quality and adequacy of topographic control.
•
•
•
•
DY6 Metals experienced geologists supervised and monitored all
processes especially during sampling and initial sample
preparation.
The samples were photographed, the remaining samples after
splitting were stored in the warehouse.
All the sample data from the field was captured electronically on a
tablet and fed directly into MX-Deposit database
Sample points were planned using ArcGIS and located in the field
using a hand-held GPS.
Commentary
•
The Grid system used is WGS_1984_UTM_Zone_36S
Data spacing for reporting of Exploration Results.
Whether the data spacing and distribution is sufficient to establish
the degree of geological and grade continuity appropriate for the
Mineral Resource and Ore Reserve estimation procedure(s) and
classifications applied.
Whether sample compositing has been applied.
•
•
Sample locations were spaced at a nominal 100m by 100m.
The nominal 100m by 100m spacing is considered sufficient for the
demonstrate an initial geological and grade continuity for this
intrusive ultramafic suite of pyroxenites and hornblendepyroxenites lithologies.
Sample compositing was applied to the whole channel sample
width.
Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering
the deposit type.
If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to have
introduced a sampling bias, this should be assessed and reported if
material.
•
The structures in the licence area and the orientation of the
orebody are known therefore a Grid sampling used ensures
unbiased sampling of the ore body.
•
Samples collected were properly sealed in sampling bags using
cable ties, labelled and stored in a locked warehouse.
• The measures taken to ensure sample security.
•
dy6metals.com | ASX:DY6
12
Audits or reviews
• The results of any audits or reviews of sampling techniques and
data.
•
During sample dispatch, a well-documented Chain of Custody was
used to ensure sample security from the sampling warehouse to
the analysis facility.
•
External audits of the sampling techniques has been done by
Addison Mining to ensure that all Standard Operating Procedures
are up to date and are accurate.
Internal audits of the sampling data, QAQC procedures was
conducted by our experienced Geologists.
•
Criteria
Mineral tenement and
land tenure status
JORC Code explanation
•
•
Exploration done by
other parties
•
Commentary
Type, reference name/number, location and ownership
including agreements or material issues with third parties
such as joint ventures, partnerships, overriding royalties,
native title interests, historical sites, wilderness or national
park and environmental settings.
The security of the tenure held at the time of reporting along
with any known impediments to obtaining a licence to
operate in the area.
•
The Ngala Hill tenure is in good standing and no known
impediments area known to exist.
The Ngala Hill EPL0510 is held 100% by Green Exploration Limited
covering an area of 15.96km2.
•
Acknowledgment and appraisal of exploration by other parties.
•
•
•
The area of Ngala Hill was mapped by the Geological Survey of
Nyasaland and its successor the Geological Survey of Malawi.
Initial sampling was completed in the 1960’s then Phelps Dodge
completed rock chip, soil sampling and trenching program in
1999-2000.
Two diamond drillholes were planned with only one drilled
which failed to reach its target.
dy6metals.com | ASX:DY6
13
•
•
•
•
Placer Dome took over the exploration completing more than
600m of trenching followed by a 4-hole diamond drilling
program with disappointing results.
In 2007 MM Mining completed a soil sampling program and
reputedly completed a drill program; no results or information
regarding this program are in the public domain.
In 2016, a private company, Sabila Capital, completed a
handheld XRF soil sampling program in 3 phases totalling 646
sample sites.
#2 Rock chip samples were also collected. A subsequent 100m x
100m soil or auger sampling program for 177 samples was
completed.
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
JORC Code explanation
Geology
• Deposit type, geological setting and style of mineralisation.
Commentary
•
The mineralisation at Ngala Hill is interpreted as a magmatic
intrusion with hydrothermal overprint. The aeromagnetic
data show a significant magnetic high associated with the
zone of mineralisation. The magnetic anomaly extends for
several kilometres beyond the outcrop. The strong
aeromagnetic anomaly associated with Ngala Hill points to
an oxidised intrusive at depth as the driving force behind the
skarnification process.
dy6metals.com | ASX:DY6
14
Drill hole Information
•
•
Data aggregation methods
•
•
•
Relationship between
mineralisation widths and
intercept lengths
•
•
A summary of all information material to the understanding
of the exploration results including a tabulation of the
following information for all Material drill holes: o easting
and northing of the drill hole collar o elevation or RL
(Reduced Level – elevation above sea level in metres) of the
drill hole collar dip and azimuth of the hole o down hole
length and interception depth o hole length.
If the exclusion of this information is justified on the basis
that the information is not Material and this exclusion does
not detract from the understanding of the report, the
Competent Person should clearly explain why this is the
case.
•
No recent drilling done and therefore no new drill hole
information to report.
In reporting Exploration Results, weighting averaging
techniques, maximum and/or minimum grade truncations
(eg cutting of high grades) and cut-off grades are usually
Material and should be stated.
Where aggregate intercepts incorporate short lengths of
high grade results and longer lengths of low grade results,
the procedure used for such aggregation should be stated
and some typical examples of such aggregations should be
shown in detail.
The assumptions used for any reporting of metal equivalent
values should be clearly stated.
•
No aggregation methods were used and no metal
equivalents are reported.
These relationships are particularly important in the
reporting of Exploration Results.
If the geometry of the mineralisation with respect to the
drill hole angle is known, its nature should be reported.
•
No new mineralisation widths are being reported. Historical
results are included for context.
dy6metals.com | ASX:DY6
15
Criteria
JORC Code explanation
• If it is not known and only the down hole lengths are reported,
there should be a clear statement to this effect (eg ‘down hole
length, true width not known’).
Diagrams
• Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported These should include, but not be limited to a plan view
of drill hole collar locations and appropriate sectional views.
•
Please see maps and diagrams included in the
announcement text, that provide locations for the samples
collected and their location relative to other projects in the
area, with known geology from government mapping.
Balanced reporting
• Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be
practiced to avoid misleading reporting of Exploration Results.
•
The release is considered to be balanced and is based on
current available data for the project area
Other substantive
exploration data
• Other exploration data, if meaningful and material, should be
reported including (but not limited to): geological observations;
geophysical survey results; geochemical survey results; bulk
samples – size and method of treatment; metallurgical test
results; bulk density, groundwater, geotechnical and rock
characteristics; potential deleterious or contaminating
substances.
•
The historical data currently available to the Company is
believed complete.
Further work
•
•
The Company intends to continue explore the tenements
taking priority samples with a view to do follow-up soil
sampling and/or drilling or trenching.
•
The nature and scale of planned further work (e.g.
tests for lateral extensions or depth extensions or large-scale
step-out drilling).
Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling
areas, provided this information is not commercially sensitive.
Commentary
dy6metals.com | ASX:DY6
16
Share your feedback
Discover